Oregon Natural Desert Association v. United States Forest Service
AI Case Brief
Generate an AI-powered case brief with:
Estimated cost: $0.10ā$0.50 per brief, depending on opinion length and retries
Full Opinion
This appeal presents the narrow question whether the United States Forest Serviceās issuance of annual operating instructions (āAOIsā) to permittees who graze livestock on national forest land constitutes final agency action for purposes of judicial review under the Administrative Procedure Act (āAPAā), 5 U.S.C. §§ 702-706. The district court held that the AOIs were not final within the meaning of Section 10(c) of the APA, 5 U.S.C. § 704, and dismissed plaintiffsā lawsuit for lack of subject matter jurisdiction. We conclude that the Forest Serviceās action in issuing the AOIs is āfinal agency actionā under § 704 and therefore that plaintiffsā claims are ripe for judicial review. Accordingly, we reverse the district courtās dismissal order and remand for a determination of the merits of plaintiffsā claims.1
I.
The Federal Land Policy and Management Act of 1976 (1701-1784), authorizes the Forest Service to allow livestock grazing on specified allotments2 within a national forest. The Forest Service authorizes and manages grazing on specified allotments by issuing (1) a grazing permit pursuant to 43 U.S.C. § 1752(a) and 36 C.F.R. § 222; (2) an Allotment Management Plan (āAMPā) pursuant to 43 U.S.C. § 1752(d) and 36 C.F.R. § 222.1(b); and (3) AOIs.3
A grazing permit is a ādocument authorizing livestock to use National Forest System or other lands under Forest Ser*980vice control for the purpose of livestock production.ā 36 C.F.R. § 222.1(b)(5); 43 U.S.C. § 1702(p). A permit grants a license to graze and establishes: (1) the number, (2) kind, (3) and class of livestock, (4) the allotment to be grazed, and (5) the period of use. See 36 C.F.R. §§ 222.1-222.4; 43 U.S.C. § 1752. The Forest Service sets these parameters based on its assessment of the landās ability to sustain average levels of livestock use according to the applicable land and resource management plan.4 See, e.g., 36 C.F.R. § 222.3(c)(1); Forest Service Handbook (āFSHā) 2209.13, § 94.2. The Forest Service generally issues permits for ten-year periods. See 36 C.F.R. § 222.3(c)(1).
The Forest Service is also required to prepare an AMP for each allotment. An AMP is āa document that specifies the program of action ... to meet [, inter 'alia,] the multiple-use, sustained yield, economic, and other needs and objectives as determined for the lands involvedā and includes provisions relating to grazing objectives āas may be prescribed by the [Forest Service], consistent with applicable law,ā 36 C.F.R. § 222.1(b); 43 U.S.C. §§ 1702(k)(l), 1752(d), including the applicable forest plan. While a forest plan is an overarching land management directive for an entire forest-wide unit within the National Forest System, the AMP is a land management directive for a specific allotment within a national forest that the Forest Service has designated for livestock grazing. See Wilderness Socāy. v. Thomas, 188 F.3d 1130, 1133 (9th Cir.1999) (describing AMPs as āsite-specificā). The AMP must be consistent with the applicable forest plan. See 16 U.S.C. § 1604(i); Neighbors of Cuddy Mountain v. Alexander, 303 F.3d 1059, 1062 (9th Cir.2002).
Finally, as reflected in the administrative record, prior to the beginning of a grazing season, the Forest Service issues an AOI to grazing permit holders. Whereas the AMP relates the directives of the applicable forest plan to the individual grazing allotment, and the grazing permit sets grazing parameters through a ten-year period, the AOI annually conveys these more long-term directives into instructions to the permittee for annual operations. See, e.g., Forest Service Manual § 2212.3 (stating that the AOI āimplements management decisions of the [AMP]ā) (chapter currently āin reserve,ā but in effect at time of district courtās order dismissing ONDAās claims). The AOI consists of a signed agreement between the Forest Service and permit holder. According to its explicit terms, the AOI is made part of the grazing permit and governs the permit holderās grazing operations for the next year.5
Because an AOI is issued annually, it is responsive to conditions that the Forest *981Service could not or may not have anticipated and planned for in the AMP or grazing permit, such as drought conditions, timing and duration of rainfall over the grazing season, success or failure of habitat restoration projects, water quality, or degree of risk to threatened or endangered species affected by grazing. See, e.g., Anchustegui v. Depāt of Agric., 257 F.3d 1124, 1126 (9th Cir.2001) (describing contents of an AOI that imposed reduced utilization levels in response to changed pasture conditions). With this contextual background in mind, we review briefly the statutory basis for ONDAās claims and the district courtās jurisdictional ruling.
II.
In 1988, Congress designated stretches of the North Fork Malheur and Malheur Rivers in the Blue Mountains of eastern Oregon as wild and scenic river corridors under the Wild and Scenic Rivers Act of 1968 (āWSRAā), 82 Stat. 907 (codified at 16 U.S.C. § 1274(a)(83), (89)). See Omnibus Oregon Wild and Scenic Rivers Act of 1988, 102 Stat. 2782. The 1990 Malheur National Forest Land and Resource Management Plan (āMalheur Forest Planā or āForest Planā) designates more than 10,-000 acres of national forest land on and adjacent to the North Fork Malheur and Malheur River corridors as livestock grazing allotments. In this action, Oregon Natural Desert Association and Center for Biological Diversity (collectively, āONDAā) challenge the Forest Serviceās decisions related to its management of livestock grazing on six of those allotments from 2000 to 2004.6 In its complaint, ONDA alleges that the Forest Service acted arbitrarily and capriciously in violation of 5 U.S.C. § 706(2)(A) by annually issuing AOIs to grazing permit holders for pastures within the protected riparian stretches of the North Fork Malheur and Malheur Rivers. ONDA alleges that the AOIs contain terms that violate the Forest Serviceās mandatory and non-discretionary duties under the WSRA, the National Forest Management Act of 1976 (āNFMAā), 90 Stat. 2949 (codified at 16 U.S.C. §§ 1600-1614), the National Environmental Policy Act of 1969 (āNEPAā), 83 Stat. 852 (codified at 42 U.S.C. § 4321 et seq.), as well as its own regulations.
In response to ONDAās action,7 the Forest Service and the intervenors moved to dismiss for lack of jurisdiction because the AOIs at issue did not constitute final agency actions reviewable under 5 U.S.C. § 706(2)(A). See ONDA v. USFS, 312 F.Supp.2d 1337, 1341-43 (D.Or.2004). The district court initially rejected their argument and ruled that under Bennett v. Spear, 520 U.S. 154, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997), the AOIs were the culmination of a process that resulted in final agency action within the meaning of § 704. See ONDA 312 F.Supp.2d at 1343. The court therefore concluded that ONDAās claims were ripe for judicial review under § 706(2)(A). Id.
Following denial of ONDAās motion for a preliminary injunction, see ONDA v. *982USFS, 2004 WL 1293909 (D.Or., June 10, 2004), the parties filed cross-motions for summary judgment and the case was transferred to a different district judge. The district court denied ONDAās motion and granted in part and denied in part the Forest Serviceās cross-motion for summary judgment. Although the district court determined that the Forest Serviceās issuance of an AOI constituted an agency action, it concluded that the agencyās action was not final and therefore not subject to judicial review under § 706(2)(A). The court also concluded that it lacked jurisdiction to review ONDAās alternative WSRA claims under § 706(1) of the APA. Accordingly, the district court dismissed ONDAās claims without prejudice. ONDA appeals the jurisdictional ruling related to its claims under § 706(2).
III.
Because the substantive statutes under' which ONDA seeks relief do not provide for a private right of action, ONDA challenges the AOIs under the judicial review provisions of the APA. See 5 U.S.C. § 702-706; Lujan v. Natāl Wildlife Fedān, 497 U.S. 871, 882, 110 S.Ct. 3177, 111 L.Ed.2d 695 (1990). To obtain judicial review under the APA, ONDA must challenge a final agency action. See 5 U.S.C. § 704; Lujan, 497 U.S. at 882, 110 S.Ct. 3177; Ukiah Valley Med. Ctr. v. FTC, 911 F.2d 261, 264 n. 1 (9th Cir.1990) (āfinality is ... a jurisdictional requirementā). For an agency action to be final, the action must (1) āmark the consummation of the agencyās decisionmaking processā and (2) ābe one by which rights or obligations have been determined, or from which legal consequences will flow.ā Bennett, 520 U.S. at 178, 117 S.Ct. 1154 (internal quotation marks omitted). ā ā[T]he core question is whether the agency has completed its deci-sionmaking process, and whether the result of that process is one that will directly affect the parties.ā ā Indus. Customers of NW Utils, v. Bonneville Power Admin., 408 F.3d 638, 646 (9th Cir.2005) (quoting Franklin v. Massachusetts, 505 U.S. 788, 797, 112 S.Ct. 2767, 120 L.Ed.2d 636 (1992)).
In determining whether an agencyās action is final, we look to whether the action ā āamounts to a definitive statement of the agencyās positionā ā or ā āhas a direct and immediate effect on the day-to-day operationsāā of the subject party, or if ā āimmediate compliance [with the terms] is expected.ā ā Indus. Customers of NW Utils, 408 F.3d at 646 (quoting Cal. Depāt of Water Res. v. FERC, 341 F.3d 906, 909 (9th Cir.2003)) (alteration in original); see also Ukiah Valley Med. Ctr., 911 F.2d at 264 (quoting FTC v. Standard Oil Co., 449 U.S. 232, 239, 101 S.Ct. 488, 66 L.Ed.2d 416 (1980)). We focus on the practical and legal effects of the agency action: ā[T]he āfinality element must be interpreted in a pragmatic and flexible manner.ā ā Or. Natural Res. Council v. Harrell, 52 F.3d 1499, 1504 (9th Cir.1995) (quoting Dietary Supplemental Coal., Inc. v. Sullivan, 978 F.2d 560 (9th Cir.1992)); Cal. Depāt of Educ. v. Bennett, 833 F.2d 827, 833 (9th Cir.1987) (āThe requirement of finality is interpreted pragmatically.ā).
The Forest Service argues that an AOI is not a final agency action because the document merely implements the Forest Serviceās other grazing decisions as found in the Forest Plan or grazing permit. Moreover, the Forest Service argues that an AOI not only lacks finality, but also does not constitute āagency actionā under the APA as interpreted by Norton v. Southern Utah Wilderness Alliance (āSUWA ā), 542 U.S. 55, 62, 124 S.Ct. 2373, 159 L.Ed.2d 137 (2004), because it is not a rule, order, license, sanction, or relief. On both bases, the Forest Service asserts that the district court lacks subject matter jurisdiction over ONDAās claims. We are *983not persuaded by the Forest Serviceās arguments. Because an AOI is properly viewed as a license within the meaning of 5 U.S.C. § 551(13), we agree with the district court that an AOI represents agency action. We disagree, however, with the district courtās determination that issuance of an AOI does not represent final agency action. As we explain below, issuance of an AOI satisfies the Bennett test for finality. It is the consummation of a process that sets the parameters for the upcoming grazing season and it imposes legal consequences on the permit holder. Thus, we conclude that ONDAās claims are ripe and that subject matter jurisdiction exists under the APA.
A. Agency Action
The Forest Service points to SUWA to support its argument that an AOI is not an agency action under the APA because, as the Court noted in that case, āagency action is limited to the specific categories defined by the APA.ā SUWA 542 U.S. at 55, 124 S.Ct. 2373. The Court rejected several environmental groupsā claims that the Bureau of Land Management (āBLMā) failed to protect certain of Utahās roadless Wilderness Study Areas from off-road vehicle use in violation of the agencyās duties under FLPMA and NEPA. 542 U.S. at 59-60, 124 S.Ct. 2373. In contrast to the āabuse of discretionā claims ONDA pursues under § 706(2), the environmental groups in SUWA had pursued their claims under § 706(1), which provides jurisdiction to ācompel agency action unlawfully withheld or unreasonably delayed.ā Id. at 61, 124 S.Ct. 2373.
In the Courtās analysis of whether the environmental groups in SUWA had properly alleged the BLMās āfailure to act,ā the Court explained the APAās meaning of agency action as defined in § 551. Id. at 62, 124 S.Ct. 2373; see also 5 U.S.C. § 701(b)(2) (āFor the purpose of this chapter ... āagency actionā ha[s] the meanin[g] given ... by section 551 of this title.ā). The Court noted that § 551(13) ābeginsā its definition of agency action with a list of ācategories of decisions made or outcomes implemented by an agency- ā -āagency rule, order, license, sanction [or] relief,ā ā which the Court described as ācircumscribed, discrete agency actions.ā SUWA, 542 U.S. at 62, 124 S.Ct. 2373 (quoting 5 U.S.C. § 551(13)) (alteration in original). The Court then noted that, under § 551(13), agency action also includes āthe equivalent or denial thereof [i.e., of an agency rule, order, license, sanction, or relief], or failure to act.ā Id. The Court concluded that although āthe equivalent thereofā is not defined in the APA, an ā āequivalent ... thereof must also be discrete.ā Id. The
Forest Serviceās argument here fails because, even undĆ©r § 551(13)ās categorical definition of agency action, an AOI is an agency action. A grazing permit is a license, Anchustegui, 257 F.3d at 1128, and the issuance of a grazing permit is an agency action under the APA. See 5 U.S.C. § 551(13); Idaho Watersheds Project v. Hahn, 307 F.3d 815, 828 (9th Cir.2002). Under the APA, a license āincludes the whole or a part of an agency permit ... or other form of permission.ā 5 U.S.C. § 551(8) (emphasis added). As discussed above, the Forest Service itself has repeatedly included a provision in the AOIs that the AOI āis made part of Part 3 of [the] Term Grazing Permit.ā An AOI is therefore properly understood to be a license for purposes of determining whether it is an agency action under the APA. Thus, we agree with the district court that issuance of an AOI is an agency action under § 551(13) of the APA.
B. Final Agency Action
1. Consummation
We next turn to whether issuance of an AOI satisfies the Bennett test *984for final agency action under the APA. To meet the first prong of the Bennett test, the challenged agency action must represent the consummation of the agencyās de-cisionmaking process.8 520 U.S. at 178, 117 S.Ct. 1154. The action āmust not be of a merely tentative or interlocutory nature.ā Id. Rather, we look to see whether the agency ā āhas rendered its last word on the matterā ā to determine whether an action is final and is ripe for judicial review. Whitman v. Am. Trucking Assān, 531 U.S. 457, 478, 121 S.Ct. 903, 149 L.Ed.2d 1 (2001) (quoting Harrison v. PPG Indus., Inc., 446 U.S. 578, 586, 100 S.Ct. 1889, 64 L.Ed.2d 525 (1980)). The administrative record establishes that an AOI is the Forest Serviceās ālast wordā authorizing an individual permit holder to graze each season.
An AOI sets forth the Forest Serviceās annual determinations regarding how much grazing particular units (pastures) within a given allotment can sustain in the upcoming season. As demonstrated by the record, in establishing the terms of an AOI, the Forest Service considers such matters as changes in pasture conditions, new scientific information, new rules that have been adopted during the previous season, or the extent of the permit holderās compliance with the previous yearās AOI. The AOI is a critical instrument in the Forest Serviceās regulation of grazing on national forest lands.
Indeed, when the Forest Service takes a site-specific action within the Malheur Forest, such as issuing a grazing permit for an allotment within the forest, the Forest Serviceās actions must comply with the standards and conditions set out in the Malheur Forest Plan as well as applicable federal environmental law. See, e.g., 42 U.S.C. § 4332(2)(C); 16 U.S.C. § 1536(a)(2). Although the Forest Service generally implements Forest Plan standards on designated grazing allotments with an AMP, none of the allotments involved in this litigation has a current AMP.9
Where an AMP does not exist for an allotment, the Forest Service has integrated the Forest Planās terms directly into the grazing permits each year through the AOI. For example, in 1996, the Forest Service issued three grazing permits for different pastures within the Bluebucket Allotment. The permits identify the general statutory and regulatory framework that governs the actions of the individual permit holders so that livestock grazing will be consistent with the Malheur Forest Plan. Part III of each grazing permit provides: āprior to completion and implementation of the scheduled individual AMPās, we will be working with you through the Annual Operating Plans [i.e., AOIs] to bring management of the Bluebucket Allotment into consistency with the terms of the Malheur [Forest Plan].ā Thus, here, the Forest Service directly āput[s] the [allotment management] decisions] into effectā through an AOI. Idaho Watersheds Project, 307 F.3d at 828.
In Idaho Watersheds Project, we held that the BLMās issuance of a grazing permit was a final agency action because āthe initial agency decisionmaker arrived at a definitive position and put the decision into *985effect by issuing the ... permits.ā Id. Here, as in Idaho Watersheds Project, the Forest Service arrived at a definitive position to allow grazing in the Malheur National Forest and put that decision into effect by issuing grazing permits. In issuing the permits, the Forest Service reserved the right to impose additional terms and conditions in light of its annual assessment of changed pasture conditions, new scientific information, new rules, and past compliance by the permit holder. As noted, the Forest Service puts these additional modifications or restrictions into effect by issuing an AOI. As the record reflects, when viewed in its proper context, the AOI represents the consummation of the Forest Serviceās annual decisionmak-ing process regarding management of grazing allotments.10
Moreover, after the Forest Service issues an AOI, the grazing permit holder is authorized to begin the new grazing season under its terms and conditions.11 Because the AOI is the only substantive document in the annual application process, it functions to do more than make minor adjustments in the grazing permit as the Forest Service asserts; pragmatically, it functions to start the grazing season. In short, the AOI is the Forest Serviceās ālast wordā before the permit holders begin grazing their livestock. Whitman, 531 U.S. at 478, 121 S.Ct. 903; cf. Ecology Ctr., Inc. v. USES, 192 F.3d 922, 925 (9th Cir.1999) (holding that monitoring and reporting under NFMA were not agency actions that consummated the Forest Serviceās decisionmaking process because they were āonly steps leading to an agency decision, rather than the final action itselfā).
The Forest Service does not contest that an AOI is the Forest Serviceās ālast wordā before a permit holder begins grazing his livestock. Rather, the Forest Service asserts that an AOI merely implements other decisions that the Forest Service has already made (i.e., the Forest Plan, AMPs, and grazing permits), and therefore is not, in itself, a final agency action. This argument, however, mis-characterizes the role of an AOI in the Forest Serviceās management of the public range. āIt is the effect of the action and not its label that must be considered.ā Abramowitz, 832 F.2d at 1075. To this end, āfinality is to be interpreted āin a pragmatic way.ā ā Oregon v. Ashcroft, 368 F.3d 1118, 1147 (9th Cir.2004) (quoting Abbott Labs. v. Gardner, 387 U.S. 136, 149-50, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967)). It is correct, as the Forest Service argues, that, in obtaining a grazing permit, the applicant agrees to comply with the Forest Plan and other applicable federal environmental requirements. However, as the administrative record demonstrates, an AOI is the only instrument that instructs the permit holder how those standards will affect his grazing operations during the upcoming season. Although the permit holder has already agreed to abide by applicable federal envi*986ronmental law in signing the term grazing permit, that acknowledgment does not diminish the force of an AOI as consummating the Forest Serviceās annual decision-making process. In sum, the issuance of an AOI represents the consummation of the Forest Serviceās determination regarding the extent, limitation, and other restrictions on a permit holderās right to graze his livestock under the terms of the permit.12
2. Legal Effect
The district court interpreted Bennett to hold that an agency action is not a final agency action unless it āalter[s] the legal regime to which the action agency is subject.ā With this understanding, the district court concluded that an AOI is not a final agency action because it does not alter the legal regime to which the Forest Service is subject. The district courtās understanding of Bennettās second prong is, however, not supported by Bennett. In Bennett, the Court held that an agency action that consummated the agencyās de-cisionmaking process (Bennettās first requirement) would be final if the action is one āby which rights or obligations have been determined, or from which legal consequences will flow.ā 520 U.S. at 178, 117 S.Ct. 1154 (internal quotation marks omitted) (emphasis added). It then held, on the facts of that case, that this second requirement was met because the challenged action altered the legal regime to which the Secretary of Interior was subject. Id. The Court did not, however, hold that alteration of the federal agencyās legal regime was the only way in which an agency action could satisfy the second finality requirement.
Courts have consistently interpreted Bennett to provide several avenues for meeting the second finality requirement. We have held that ā[t]he general *987rule is that administrative orders are not final and reviewable āunless and until they impose an obligation, deny a right, or fix some legal relationship as a consummation of the administrative process.ā ā Ukiah Valley Med. Ctr., 911 F.2d at 264 (quoting Chi & S. Air Lines, Inc. v. Waterman S.S. Corp., 333 U.S. 103, 113, 68 S.Ct. 431, 92 L.Ed. 568 (1948)) (emphasis added). The legal relationship need not alter the legal regime to which the involved federal agency is subject. See, e.g., Alaska Depāt of Envtl. Conservation v. EPA 540 U.S. 461, 482-83, 124 S.Ct. 983, 157 L.Ed.2d 967 (2004) (holding that EPAās order under the Clean Air Act prohibiting the Alaskan Department of Environment from issuing permits to a zinc mining company was a final agency action because the order effectively halted construction of the mine through the threat of civil and criminal penalties, despite lack of alteration of EPAās legal regime); Cal. Depāt of Educ., 833 F.2d at 833 (holding that the Department of Educationās letter informing state that interest would accrue was a final agency action despite lack of alteration of the Departmentās legal regime); Idaho Watersheds Project, 307 F.3d at 828 (holding that BLMās issuance of grazing permits constituted final agency action despite lack of alteration of BLMās legal regime). These cases demonstrate that Bennettās second requirement can be met through different kinds of agency actions, not only one that alters an agencyās legal regime.
Indeed, we have said that an agency action may be final if it has a ā ādirect and immediate ... effect on the day-to-day businessā of the subject party.ā Ukiah Valley Med. Ctr., 911 F.2d at 264 (quoting Standard Oil, 449 U.S. at 239, 101 S.Ct. 488). We consider āwhether the [action] has the status of law or comparable legal force, and whether immediate compliance with its terms is expected.ā Id. In light of these rules, we turn to whether an AOI has any legal effect that would qualify it as a final agency action under Bennettās second finality requirement.
In Anchustegui the plaintiff challenged the governmentās attempt to impose sanctions for his failure to comply with restrictions on cattle grazing delineated in an AOI. 257 F.3d at 1126. We noted, as described above, that the Forest Service uses the AOI to set annual grazing specifications for the permit holder. Notably, we recognized that an AOI contains ādirectivesā that, if not followed, can trigger the Forest Service to institute agency proceedings against the subject grazing permittee. Id. at 1126-28. While An-chustegui does not principally concern the function of an AOI, it aids our understanding that an AOI carries legal consequences. The administrative record in this appeal also supports this conclusion.
a. Notices of Non-Compliance and Threatened Permit Action Against Howard and Butler Ranches
If a permittee does not comply with the directives in the AOI, the Forest Service can issue a Notice of Non-Compliance (NONC) to the permit holder. See Anchustegui, 257 F.3d at 1129 (explaining administrative notice process under 5 U.S.C. § 558(b),(c), with which Forest Service must comply before taking āpermit actionā). As the record demonstrates, the Forest Service issued a NONC to the Howard Ranch on July 14, 2004. Howard Ranch obtained a grazing permit for pastures within the Bluebucket Allotment in 1996. The 2004 AOI recommended that the Ranch monitor certain āmove triggersā to increase the likelihood of moving its livestock before reaching utilization limits. It also stated a reduction in Howard Ranchās 2004 āAllowable Use Standardsā based on the allotmentās classification in the Malheur Forest Plan and consultation requirements under the Endangered Spe*988cies Act of 1973 (āESAā), 87 Stat. 884 (codified at 16 U.S.C. §§ 1531-43). The NONC informed Howard Ranch of its failure to meet conditions in both its grazing permit and its AOI, including exceeding utilization standards and failing to follow the 2004 AOI grazing schedule for pasture moves.13
On January 26, 2005, the Forest Service notified Howard Ranch that it decided to take āpermit actionā by suspending 25% of the Ranchās permitted head of livestock, as warned in the NONC. The notification identified violations of the AOI and imposed a modification of the underlying grazing permit as the appropriate sanction for the violation. See also 36 C.F.R. § 222.4(a)(4) (authorizing Forest Service to cancel or suspend grazing permit if permittee does not comply with provisions and requirements of permit or governing regulations).
Similarly, in a separate NONC to Butler Ranch for violation of the 2004 North Fork Allotment AOI, the Forest Service stated: āFailure to follow the direction set forth in the Annual Operating Instructions and my August 6 letter, and exceeding allowable use standards is a violation of ... the terms and conditions set forth in your Term Grazing Permit,ā and threatened similar permit action to that taken against Howard Ranch. The Butler Ranch NONC cited permit sections that authorize the Forest Service to cancel or suspend a permit for failure to comply with, inter alia, the allotment management plan. As with each grazing permit involved in this appeal, this permit covered an allotment which did not have an operative allotment management plan. Thus, the permit specified that the Forest Service would enforce the Forest Plan standards, as adjusted annually with range conditions, via the AOI. The Howard and Butler Ranchesā NONCs demonstrate the AOIās legal effect: failure to comply with the AOIās substantive terms can result in administrative sanctions against the permit holder.
The Forest Service argues that because the sanction for an AOI violation is against the permit, the AOI has no legal effect. However, as the district court noted in its ruling denying the Forest Serviceās motion to dismiss, ā[s]imply because an AO[I]ās authority is drawn from the permit does not make the agencyās decision reflected in the AO[I] any less of a final agency action.ā ONDA, 312 F.Supp.2d at 1343. Rather, that an AOI violation can prompt the Forest Service to take enforcement action against the non-complying permit-tee is a show of the AOIās ālegal forceā and the Forest Serviceās expectation of āimmediate compliance with its terms.ā Ukiah Valley Med. Ctr., 911 F.2d at 264.
b. AOI Used to Impose Bull Trout ESA Standards
The legal effect of an AOI is also demonstrated by the Forest Serviceās use of the AOI to impose standards promulgated in the wake of the 1998 listing of the bull trout, a native salmonid species, as a threatened species under the ESA. As documented in the record, the Forest Service issued a grazing permit to Coombs Ranch for the Dollar Basin/Star Glade Allotments in 1996. The permit stated that no AMP existed for the allotments, but that the *989Forest Service was scheduled to develop one. It also stated that, in the meantime, the Forest Service would use the AOI āto bring management of the [allotments] into consistency with the terms of the Malheur [Forest Plan].ā In 1998, the Fish and Wildlife Service (āFWSā) listed the bull trout as a threatened species under the ESA, 63 Federal Reg. 31,647 (June 10, 1998), which triggered the Forest Serviceās duty under the ESA to consult with FWS to insure that any agency action, such as authorization of grazing, on Forest Service land would not likely jeopardize the threatened species or its habitat. See 16 U.S.C. § 1536(a)(2).
Since the 1998 listing, the relevant AOIs have incorporated bull trout standards and objectives. For example, the 1998 AOI for Dollar Basin/Star Glade allotments stated, ā[b]eginning this year, standards and habitat objectives for bull trout are detailed for each unit.ā The administrative record further reflects that AOIs for the other allotments subject to bull trout standards and objectives also contained similar statements between 1998-2003. Because the Forest Service issued most of the grazing permits underlying the AOIs challenged in this litigation prior to the bull trout listing and there are no current AMPs for the allotments, the AOI was the Forest Serviceās principal means of imposing the new bull trout standards on the permit holders from 1998 forward. By restricting the rights of and conferring duties on a grazing permit holder to bring the Forest Serviceās annual authorization of grazing into compliance with ESA requirements, the AOI is the Forest Serviceās definitive statement that fixes the legal relationship between the Forest Service and the permit holder. The utilization of an AOI in this manner further supports our conclusion that an AOI is a final agency action. See Idaho Watersheds Project, 307 F.3d at 828 (ādefinitive positionā); Ukiah Valley Med. Ctr., 911 F.2d at 264 (āfix some legal relationshipā).
Finally, the Forest Service argues that ā[w]ithout the AOIs, the permittees would still be authorized to graze in accordance with the terms and conditions of the permit.ā The Forest Serviceās position is contradicted by the terms of the grazing permit itself and Forest Service practice. The permit does not authorize the permit holder to graze continuously for the permitās ten-year duration. Rather, the permit authorizes the permit holder to graze livestock only after the Forest Service has approved the permitteeās annual application. In practice, the Forest Service approves the application in conjunction with issuance of the AOI. Although the annual application calls for basic information, it is the AOI that indicates the detailed terms and conditions by which the F