AI Case Brief
Generate an AI-powered case brief with:
đKey Facts
âïžLegal Issues
đCourt Holding
đĄReasoning
đŻSignificance
Estimated cost: $0.10â$0.50 per brief, depending on opinion length and retries
Full Opinion
UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF MISSISSIPPI NORTHERN DIVISION BECKER CONTRACTOR SERVICES, INC. PLAINTIFF V. CIVIL ACTION NO. 3:23-CV-3034-DPJ-ASH QUIKTRIP CORP. and CDI DEFENDANTS CONTRACTORS, LLC ORDER This construction case between a general contractor and its subcontractor disputes who owes whom. Defendant QuikTrip Corporation hired Defendant CDI Contractors, LLC as its general contractor to build a service station. CDI then subcontracted with Plaintiff Becker Contractor Services, Inc. to construct storm drainage for the project. Becker and CDI both say the other breached their duties under that subcontract. There are two pending summary-judgment motions: (1) a joint motion by Defendants QuikTrip and CDI [38] on Beckerâs claims against them and (2) CDIâs motion [36] seeking judgment as to some counterclaims it asserted against Becker. As will be discussed, the Court grants Defendantsâ motion dismissing Beckerâs conversion claim and dismisses Beckerâs now- conceded misrepresentation claim. The Court denies everything else. That said, it is a close call whether Defendants should also prevail on other claims or parts of other claims (i.e., specific disputed costs). But no matter how the Court rules on the other issues, the case would still proceed to trial because some of CDIâs counterclaims are not disputed under Rule 56. In addition to those jury questions, Becker has claims that present fact questions. And because the borderline claims seem intermingled with ones that must be tried, it is more prudent to allow the case to proceed. As the Fifth Circuit has observed, â[e]ven if the standards of Rule 56 are met, a court has discretion to deny a motion for summary judgment if it believes that âthe better course would be to proceed to a full trial.ââ Firman v. Life Ins. Co. of N. Am., 684 F.3d 533, 538 (5th Cir. 2012) (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255 (1986)). I. Background In March 2022, CDI requested bids for building a new QuikTrip gas station in Byram, Mississippi. Defs.â Mem. [39] at 1; P. Becker Aff. [42-1] ¶ 3. Becker offered to provide storm drains and utilities, and CDI accepted in April 2022. Id.; CDI email [38-2] at 1. But it took until September 2022 for Becker to sign the subcontract because it had trouble obtaining the insurance coverage that CDI required. Defs.â Mem. [39] at 2. Despite the time lag, Becker didnât ask for any inflation-based changes to its bid. The problems continued after work began. In general, Becker says CDI refused to pay for extra-contractual work it instructed Becker to perform, while CDI says Becker failed to properly document its change order requests and started the extra work without receiving written approval as the subcontract required. There were other disputes too, but most issues relate to the change orders requests. Becker eventually obtained a lien against Defendants on March 30, 2023, Lien [1-1] at 26, and a month later walked off the job taking key materials with it, P. Becker Aff. [42-1] ¶ 21. CDI believes this breached Beckerâs duty under the subcontract to proceed with work while the parties addressed pay disputes. Eventually Becker and CDI negotiated Beckerâs return to the site, and it completed its scope of work. But CDI withheld money Becker felt owed.1 1 The parties have not yet adequately addressed the legal consequences of the negotiated return to work. For example, would it be considered a ratification? The Court has not examined the question and merely flags it as a potential issue moving forward. In September 2023, Becker sued Defendants on various grounds including breach of contract. CDI removed [1] the case, joined [4] by QuikTrip. CDI also asserted counterclaims against Becker. Ans. and Counterclaims [7] at 13â17. Defendants based their removal on diversity jurisdiction under 28 U.S.C. § 1332, and the Court finds that subject-matter jurisdiction does exist. It therefore considers the pending motions. II. Standard Summary judgment is warranted under Federal Rule of Civil Procedure 56(a) when evidence reveals no genuine dispute about any material fact and the moving party is entitled to judgment as a matter of law. The rule âmandates the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a showing sufficient to establish the existence of an element essential to that partyâs case[ ] and on which that party will bear the burden of proof at trial.â Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). The party moving for summary judgment âbears the initial responsibility of informing the district court of the basis for its motion[ ] and identifying those portions of [the record] which it believes demonstrate the absence of a genuine issue of material fact.â Id. at 323. The nonmoving party must then âgo beyond the pleadingsâ and âdesignate âspecific facts showing that there is a genuine issue for trial.ââ Id. at 324 (citation omitted). 2 In reviewing the evidence, factual controversies are to be resolved in favor of the nonmovant, âbut only when . . . both parties have submitted evidence of contradictory facts.â Little v. Liquid Air Corp., 37 F.3d 1069, 1075 (5th Cir. 1994) (en banc). When such 2 Beckerâs response doesnât always comply with this rule. For example, it includes over 150 pages of business records but rarely cites to the particular parts of those records as Rule 56(c) requires. The Court is under no duty to search the record for evidence supporting a partyâs position. Fuentes v. Postmaster Gen. of U.S. Postal Serv., 282 F. Appâx 296, 300 (5th Cir. 2008). contradictory facts exist, the court may ânot make credibility determinations or weigh the evidence.â Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150 (2000). It must âinterpret all facts and draw all reasonable inferences in favor of the nonmovant.â EEOC v. Rite Way Serv., 819 F.3d 235, 239 (5th Cir. 2016); accord Tolan v. Cotton, 572 U.S. 650, 660 (2014). But conclusory allegations, speculation, unsubstantiated assertions, and legalistic arguments have never constituted an adequate substitute for specific facts showing a genuine issue for trial. TIG Ins. Co. v. Sedgwick James of Wash., 276 F.3d 754, 759 (5th Cir. 2002) (citing SEC v. Recile, 10 F.3d 1093, 1097 (5th Cir. 1993)). III. Discussion This Order first considers the applicable law. It then addresses three claims that require individual treatment: (1) Beckerâs lien-based claim, (2) Beckerâs conversion claim, and (3) CDIâs conversion claim. All other claimsâincluding CDIâs counterclaims against Beckerâwill be addressed collectively. A. Applicable Law To start, the Court considers which stateâs law applies. Both Becker and CDI bring claims under the subcontract, which elects Arkansas law. Subcontract [38-3] § 14.1. But they briefed both motions under Mississippiâs substantive law, never mentioning the choice-of-law clause or any Arkansas law. Briefing a case under one stateâs laws without raising choice-of-law waives the issue. Fruge v. Amerisure Mut. Ins. Co., 663 F.3d 743, 747 (5th Cir. 2011). The Court accepts the partiesâ implicit agreement to apply Mississippi law.3 3 The same goes for the subcontractâs forum-selection clause, which places exclusive jurisdiction and venue in an Arkansas county. Subcontract [38-3] § 14.1; see also SGIC Strategic Glob. Inv. Cap., Inc. v. Burger King Eur. GmbH, 839 F.3d 422, 426 (5th Cir. 2016) (explaining waiver of forum); Breal v. Downs L. Grp., 376 So. 3d 1221, 1225 (Miss. 2023) (holding party waived forum selection by litigating over a year in Mississippi). B. Beckerâs Lien-Based Claim Becker filed its construction lien against QuikTrip under Mississippi Code section 85-7-401 et seq. Lien [1-1] at 26. QuikTrip denies the lienâs validity based on Beckerâs lack of âsubstantial compliance . . . with the . . . subcontract.â Miss. Code Ann. § 85-7-405. So, as presented, whether Becker has an enforceable lien depends on whether it substantially complied with the subcontract. The Mississippi Supreme Court has explained âsubstantial performanceâ of a construction contract: substantial performance is not literal, full or exact performance in every slight or unimportant detail, but performance of all important particulars; and . . . substantial performance exists where the building or structure as a whole is not impaired, where it can be used for its intended purpose after erection, where the defects can be remedied without any great expenditure and without material damage to other parts of the structure and may without injustice be compensated for by deductions from the contract price. Garner v. Hickman, 733 So. 2d 191, 196 (Miss. 1999) (quoting Bevis Constr. Co. v. Kittrell, 139 So. 2d 375, 379 (Miss. 1962)). Substantial performance is essentially the inverse of material breach: if the contract was substantially performed, there was no material breach. See Measday v. Kwik-Kopy Corp., 713 F.2d 118, 124 (5th Cir. 1983) (citing J. Calamari and J. Perillo, The Law of Contracts § 11â14 (1977)). This definition fits with Mississippi law, under which a material breach means âa failure to perform a substantial part of the contract or one or more of its essential terms or conditions, or if there is such a breach as substantially defeats its purpose.â UHS-Qualicare, Inc. v. Gulf Coast Cmty. Hosp., Inc., 525 So. 2d 746, 756 (Miss. 1987) (emphasis added) (quoting Gulf S. Cap. Corp. v. Brown, 183 So. 2d 802, 805 (Miss. 1966)). The cases QuikTrip cites donât conflict with this definition. One involved a subcontractor that walked out and never returned, leaving the project â50â60% complete.â Haden v. Krupp Asset Mgmt. Corp., 776 F. Supp. 1151, 1156 (S.D. Miss. 1990). In another, the contractor terminated the contract, alleging default. Mergentime Corp. v. Wash. Metro. Area Transp. Auth., No. CIV. 89-1055, 2006 WL 416177, at *1 (D.D.C. Feb. 22, 2006). Becker walked off but then returned and finished its contract. CDI never terminated Becker despite the alleged delays and Beckerâs decision to walk off the job. CDI instead negotiated Beckerâs return, and the work continued to completion. It also remains a fact question whether the other issues between the parties were enough to say Becker failed to substantially comply as section 85-7-405(1)(a) requires. So absent another argument from QuikTrip, the Court denies summary judgment on Count One of the Complaint.4 C. Beckerâs Conversion Claim Against CDI Becker says âCDI has exercised dominion and control over funds and converted funds by selling, transferring or using the funds without Beckerâs permission or consent and without accounting to Becker for the funds.â Compl. [1-1] ¶ 47. CDI objects that a conversion action isnât usually available for deprivation of money. Defs.â Mem. [39] at 19 (citing Grand Biscayne 670, LLC v. 14510 Lemoyne Blvd., LLC, 1:18-CV-357-HSO-JCG, 2019 WL 1714477, at *3 (S.D. Miss. Apr. 17, 2019)). Under Mississippi law, âthe tort of conversion cannot be used to recover a mere debt.â McGee v. Comprehensive Radiology Servs., PLLC, 340 So. 3d 328, 330 (Miss. 2022). Thus, âwhere there is no obligation to return identical money, but only a relationship of debtor and creditor, an action for conversion of the funds representing the indebtedness will not lie against the debtor.â Id. (emphasis in original) (quoting Mossler Acceptance Co. v. Moore, 67 So. 2d 4 Even if QuikTrip met its burden under Rule 56, the lien issues overlap other issues that will proceed, so taking this one to trial is âthe better course.â Firman, 684 F.3d at 538. 868, 873 (Miss. 1953)). That does not mean that money can never be converted. Id. Indeed, that happened in McGee, when one party collected money for the other and held it in an escrow account. Id. at 334. The conversion claim prevailed because the money âwas easily identifiable.â Id. (affirming judgment). Becker argues that while âall unpaid amounts submitted to CDI for Additional Work were converted by CDI, one category of unpaid funds was unquestionably âearmarkedâ for payment to Becker: retainage.â Pl.âs Mem. [42] at 12. It offers neither legal authority nor record evidence that support this position. Starting with the suggestion that CDI converted all unpaid amounts, those were âmere debts,â and Becker doesnât argue otherwise. McGee, 340 So. 3d at 330. As for the retainage, itâs hypothetically possible that such obligations couldâwith appropriate factsâsupport a conversion claim. That could be true if, for example, the money was somehow âidentifiableâ and a party had to return the âidentical funds.â Id. But Becker offers no record evidence explaining how the funds were collected or held. So unlike McGee, there is no cited evidence showing that the funds were anything but a âmere debt.â Id. The same thing happened in Vercon Construction, Inc. v. Highland Mortgage. Co., No. 3:03-1370, 2005 WL 6158875, at *4 (D.S.C. July 21, 2005), affâd, 187 F. Appâx 264 (4th Cir. 2006). There, the court granted summary judgment on a conversion claim related to retainage because the retainage in that construction contract â[was] not an identifiable or separate item.â Id. (citation and quotation marks omitted); see also U. S. Fid. & Guar. Co. v. Bass, 619 F.2d 1057, 1061 (5th Cir. 1980) (holding under Alabama law that funds âmerely credited to a particular retainage accountâ could not be subject of conversion because there was âno obligation to return the identical money, but only a relationship of debtor or creditorâ) (citation omitted). Without any legal authority or record evidence supporting Beckerâs position, summary judgment is granted on this claim. D. CDIâs Conversion Claim CDI claims that Becker converted specialized âtrench drainâ piping called âHydroblock.â See CDI Mem. [37] at 3. Under the subcontract, CDI paid Becker $44,000 to procure the Hydroblock, but by the time Becker signed the subcontract, the price had risen to over $61,000. Becker says it sent the $44,000 to the vendor, but the vendor applied the money to other purchases Becker made for other projects and then demanded full payment at the new price. P. Becker Aff. [42-1] ¶¶ 16, 24â26. According to Becker, it lacked resources to make that payment because CDI refused to pay for other work, so Becker walked off the job and took the Hydroblock with it. Id. ¶¶ 16â21. Becker eventually returned the Hydroblock and completed the work after reaching a new deal with CDI. Id. ¶¶ 25â28. But CDI claims that Becker had no right to take the Hydroblock in the first place. âTo make out a conversion, there must be proof of a wrongful possession, or the exercise of a dominion in exclusion or defiance of the ownerâs right, or of an unauthorized and injurious use, or of a wrongful detention after demand.â Smith v. Franklin Custodian Funds, Inc., 726 So. 2d 144, 149 (Miss. 1998) (quoting Miss. Motor Fin., Inc. v. Thomas, 149 So. 2d 20, 23 (Miss. 1963)). There is no dispute Becker took the Hydroblock, even if temporarily. But CDI seems to acknowledge that it did not own the materials. The question therefore is whether CDI must show that it did. Becker says it must because â[i]t is elementary that ownership is an essential element of conversion.â Pl.âs Mem. [41] at 5 (quoting Helveston v. Lum Props. Ltd., 2 So. 3d 783, 789 (Miss. Ct. App. 2009) (quoting Cmty. Bank v. Courtney, 884 So. 2d 767, 772â73 (Miss. 2004))). The Mississippi Supreme Court applied that rule in Courtney, holding: âBecause Courtney did not own [the repossessed] items, and ownership is an essential element of conversion, the trial court erred in denying the Bankâs j.n.o.v. as to those items.â 884 So. 2d at 773. CDI never acknowledges this binding authorityâeven in reply. It relies instead on out- of-state cases, a 1917 dissenting opinion from the Mississippi Supreme Court, and a district- court case from Mississippi that predated Courtney. See CDI Reply [45] at 9. CDI will need to address Courtney before it is entitled to judgment. CDI alternatively argues that Becker converted the money CDI spent on the Hydroblock. But CDI needs to explain why that would not be a âmere debt.â McGee, 340 So. 3d at 330. And even if it could, whose money âultimatelyâ did CDI spend, its own or QuikTripâs? The Court is not suggesting that this claim cannot survive; it merely holds that CDI is not entitled to summary judgment. Additional briefing may be necessary at trial. E. Remaining Claims Defendants seek summary judgment on Beckerâs remaining claims, and CDI separately seeks summary judgment on some counterclaims against Becker. The Becker claims mostly relate to unpaid extra work and include (1) breach of contract against CDI, (2) breach of the duty of good faith and fair dealing against CDI, (3) quantum meruit and unjust enrichment against both Defendants, (4) punitive damages against CDI, and (5) statutory attorneyâs fees, penalties, and interest against CDI. The remaining CDI counterclaims relate to Beckerâs work stoppage despite a duty-to- proceed clause that required it to âcarry on the Work and maintain the Schedule of Work pending final resolution of a claim.â Subcontract [36-3] § 11.4. Those claims include (1) breach of contract, (2) breach of the duty of good faith and fair dealing, (3) punitive damages, and (4) attorneysâ fees and costs. There are other counterclaims CDI did not raise in its motion. The claims and counterclaims are largely interrelated and turn on Beckerâs assertion that it was entitled to payment for the extra work it performed before walking off the job. This is a common dispute in the construction industry that is well described in one of the leading treatises on construction law. See CDI Reply [45] at 3 (citing 5 Bruner & OâConnor, Construction Law § 18:26). CDI cites Bruner & OâConnor for its comment on duty-to-proceed clauses like § 11.4 of the subcontract: â[T]he contractor is expected to proceed with the work at its own expense until the dispute is resolved. The contractorâs failure to do so is a material breach.â Bruner & OâConnor, Construction Law § 18:26. But Bruner & OâConnor doesnât stop there. The next sentence states that such breaches may be justified when the owner improperly denies payment for change orders: The inherent problem in withholding payment on an undercapitalized contractor is that it can commence the âdownward spiralâ of contract nonperformance, and, if unjustified, can be viewed as a material breach of contract. Slow-down in performance due to nonpayment begets more withholding. Wrongful withholding of payment by the owner justifies contract termination by the contractor. . . . In the construction industry, the most frequent sources of payment disputes have arisen over entitlement to payment for changes and extras, and over failure of the paying party to properly administer the contractual change order process. Refusal to acknowledge that work is extra and beyond the scope of the contract, and wrongful denial of compensation for changed work have led to many findings of material breach. Negotiation in good faith of adequate change order compensation is an implied material obligation which, if breached, may justify termination for cause. Id. So too here, Beckerâs entitlement to payment for the extra work presents a threshold question for its claim that CDI breached the subcontract by failing to pay and for whether Becker breached the subcontract by stopping work.5 Whether Becker was entitled to extra compensation starts with a few facts that have not been disputed. First, the project was behind, and CDI was pressing Becker to get it done. See Defs.â Reply [46] at 2. Second, the project encountered additional work or expenses beyond what the subcontract provided. P. Becker Aff. [42-1] ¶ 4. Third, Becker often did that work before CDI approved its change-order requests in writing. Id. ¶ 9. CDI says that violated the subcontractâs article 12 governing changes to the subcontractâs scope. To start, § 12.1 states that âSubcontractor [Becker] shall perform any and all changes . . . when specifically ordered to do so in writing by CDI.â Subcontract [36-3] at 14. That provision also states that Becker must provide within 14 days of those orders its estimate of costs including details and documentation. Id. Section 12.2.2 then stresses that CDI would make no payments above the subcontracted amount âunless specifically authorized, in writing, and approved by the Project Manager before the extra work is done.â âGenerally, a contractor who proceeds with work without procuring a written change order proceeds at his peril.â City of Mound Bayou v. Collins, 499 So. 2d 1354, 1358 (Miss. 1986). But as Becker points out, Mississippi law allows a contractor to recover for work outside 5 Not every claim Becker makes turns on this analysis. For example, the job included additional work for damaged clean outs, but the parties dispute who completed that work. Both sides support their position with sworn testimony. See P. Becker Aff. [42-1] ¶ 8; King Dep. [38-11] at 151. Beckerâs affidavit is competent on this point, and the Court must âconstrue all facts and inferences in the light most favorable to the nonmoving party.â Murray v. Earle, 405 F.3d 278, 284 (5th Cir. 2005) (citation omitted). Given the extent to which the issues interrelate, the Court will not go through each disputed expense, but the clean-out dispute shows a claim for which a jury question exists. a change order âif the extra work was âorally ordered, requested, directed, authorized or consented [to] by the owner or his duly authorized agent.ââ Tupelo Redev. Agency v. Gray Corp., 972 So. 2d 495, 507 (Miss. 2007) (quoting Collins, 499 So. 2d at 1358). Thatâs true even with contracts like this one that require written approval. Any âwriting requirement contained in the contract could itself be waived by the subsequent conduct of the parties.â Id. (quoting Canizaro v. Mobile Commcâns Corp., 655 So. 2d 25, 29 (Miss. 1995)). Among the acts or conduct amounting to waiver are the ownerâs knowledge of, agreement to, or acquiescence in such extra work, a course of dealing which repeatedly disregards such stipulation, and a promise to pay for extra work, orally requested by the owner and performed in reliance on that promise. Eastline Corp. v. Marion Apts., Ltd., 524 So. 2d 582, 584 (Miss. 1988). â[A] persistent pattern of conductâ can amount to waiver of the change-order requirement, which presents âa proper jury questionâ that âdepended upon the facts.â Gray Corp., 972 So. 2d at 507. In Eastline, for example, the contractor was under pressure to finish the job and performed work before written approval. 524 So. 2d at 584. But its vice president maintained that when he requested authorization for that work, the owner told him: âGet the project done. Get it done. Weâll take care of it later.â Id. The trial court refused to admit evidence that the owner (Marion) waived the contractâs written-approval provision, but the Mississippi Supreme Court reversed and remanded for a full trial: The evidence appears to support that Eastline acted in good faith when it proceeded with additional work without obtaining the necessary change orders; that Marion had knowledge of Eastlineâs performance of additional work; that Marion promised to pay for the additional work and Eastline obtained this assurance before proceeding; and that Marionâs acquiescence in the additional work is evidenced by its agentâs signature on the certificate of substantial completion. Id. at 585. Much like in Eastline, Becker claims CDI âfailed to issue written change orders even though they expected Becker to complete the work.â P. Becker Aff. [42-1] ¶ 5. And âCDI would often instruct Becker to do the additional work in the absence of a written change order and give [Peter Becker] verbal assurances that Becker would be compensated for such Additional Work.â Id. ¶ 6. Becker then provides examples. See id. ¶¶ 7â10. He says CDI knew the work it ordered was critical and was proceeding without written approval. See, e.g., id. ¶ 9. Becker has created a fact question whether Defendants waived the writing requirement and should have paid for the extra work.6 As noted, the other claims cascade from this one. For example, Becker may not have breached the subcontract by walking off the job if CDIâs failure to pay was unjustified. See Bruner & OâConnor, Construction Law § 18:26. And that open question leaves a fact issue whether either party should prevail on its bad-faith claims. Id.; see also Cenac v. Murry, 609 So. 2d 1257, 1272 (Miss. 1992) (addressing bad-faith claims) (citing Restatement (Second) of Contracts § 205 (1979)). So too, the retainage issueâas briefedâseems related in part to the validity of Beckerâs lien. See Defs.â Mem. [39] at 14â15. Thus, this fact question permeates the remaining claims. 6 CDI says âself-serving affidavits [like Peter Beckerâs], without more, will not defeat a motion for summary judgment.â Defs.â Reply [46] at 6 (emphasis added) (quoting Williams v. Vanderbilt Mortg. & Fin., Inc., No. 3:11-CV-613-DPJ-FKB, 2013 WL 5965689, at *4 (S.D. Miss. Nov. 8, 2013)). âA partyâs own testimony is often âself-serving,â but we do not exclude it as incompetent for that reason alone.â C.R. Pittman Constr. Co., Inc. v. Natâl Fire Ins. Co. of Hartford, 453 F. Appâx 439, 443 (5th Cir. 2011) (citation omitted). âInstead, an affidavit based on personal knowledge and containing factual assertions suffices to create a fact issue, even if the affidavit is arguably self-serving.â Id. Beckerâs affidavit on these issues is not merely âconclusory and self-serving.â DIRECTV, Inc. v. Budden, 420 F.3d 521, 531 (5th Cir. 2005). He has personal knowledge about what CDI told him and about the work being done, and he includes examples. The Court recognizes that some claims may ultimately lack merit. But with issues destined for trialâand given the intermingled facts and legal theoriesââthe better course would be to proceed to a full trial.â Firman, 684 F.3d at 538. If a party fails to meet its burden at trial, then the matter can be revisited on directed verdict. For example, it does appear that Mississippi law bars Becker from recovering under a quasi-contract theory like quantum meruit or unjust enrichment when an express contract exists covering the same claims. Watkins Dev., LLC v. Jackson Redev. Auth., 283 So. 3d 170, 178 (Miss. 2019). But because thatâs only an alternative legal theory based on the same facts as Beckerâs claim for breach of contract, Defendants suffer no prejudice by allowing the claim to remain in the suit for now.7 IV. Conclusion The Court has considered all arguments presented. Any not expressly addressed here would not affect the outcome. The Court grants summary judgment for CDI [38] on Beckerâs conversion and misrepresentation claims. Otherwise, the Court denies Defendantsâ motion for summary judgment [38] and CDIâs motion for summary judgment on its counterclaims [36]. The parties are instructed to contact the Courtroom Deputy to set the case for pretrial conference and trial. SO ORDERED AND ADJUDGED this the 7th day of March, 2025. s/ Daniel P. Jordan III UNITED STATES DISTRICT JUDGE 7 It seems the parties were somewhat unsure about the specific costs that are disputed. For instance, CDIâs opening brief [39] assumes Becker was disputing certain expenses. But Becker ignored most of those and listed others in its response. See Pl.âs Mem. [42] at 7. Beckerâs response may now frame the issues, but the parties should identify the specific disputes in the proposed pretrial order.
Case Information
- Court
- S.D. Miss.
- Decision Date
- March 7, 2025
- Status
- Precedential