AI Case Brief
Generate an AI-powered case brief with:
đKey Facts
âïžLegal Issues
đCourt Holding
đĄReasoning
đŻSignificance
Estimated cost: $0.10â$0.50 per brief, depending on opinion length and retries
Full Opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) West Point Utilities, LLC ) ASBCA No. 63006 ) Under Contract No. N62473-19-D-1206 ) Task Order No. N62473-20-F-4216 ) APPEARANCES FOR THE APPELLANT: Kirk E. Niemi, Esq. David B. Wonderlick, Esq. Varela, Lee, Metz & Guarino, LLP Tysons Corner, VA APPEARANCES FOR THE GOVERNMENT: Allison M. McDade, Esq. Navy Chief Trial Attorney Sharon G. Hutchins, Esq. Trial Attorney OPINION BY ADMINISTRATIVE JUDGE WOODROW ON THE GOVERNMENTâS MOTIONS TO STRIKE AND FOR SUMMARY JUDGMENT This appeal arises from a default termination under an Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) for wet utilities construction projects. In November 2018, the Naval Facilities Engineering Command Southwest (NAVFAC or Navy) awarded West Point Utilities, LLC (West Point) a $249 million MACC covering construction, renovation, and repair projects across six western states. The dispute centers on Task Order No. N62473-20-F-4216 for water treatment plant repairs at Naval Air Facility El Centro, California, with an original completion date of September 22, 2021, later extended to May 12, 2022. Following performance delays and West Pointâs responses to cure and show cause notices, the contracting officer terminated West Point for default. West Point challenges this termination and seeks conversion to a termination for convenience, while also alleging additional damages and a breach of its fair opportunity to compete for future task orders. This matter comes before us on the Navyâs motion seeking dismissal of Counts I and II of West Pointâs complaint for lack of jurisdiction and for summary judgment upholding the default termination. We hold that: (1) the Board lacks jurisdiction over West Pointâs claims for monetary damages and breach of fair opportunity to compete absent certified claims to the contracting officer; and (2) genuine issues of material fact preclude summary judgment upholding the default termination. Accordingly, we grant the governmentâs motion to dismiss for lack of jurisdiction to entertain the allegations set forth in paragraphs 84, 85, and Count II (paragraphs 88-91) of West Pointâs complaint and, therefore, strike those allegations. 1 Finally, we deny the governmentâs motion for summary judgment and lift the stay entered pursuant to our November 29, 2021 Order. The government shall file an answer to appellantâs complaint no later than 40 days from the date of this decision. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION 1. On November 14, 2018, NAVFAC awarded to West Point - Granite JV, LLC (West Point) Contract No. N62473-19-D-1206, an Indefinite Delivery Indefinite Quantity (IDIQ), Small Business Multiple Award Construction Contact (MACC), for new construction, renovation, and repair of wet utilities construction projects at various Government installations located in California, Arizona, Nevada, Utah, Colorado, and New Mexico. The maximum dollar amount for all the contracts combined was $249,000,000, with an estimated task order range of $300,000 to $20,000,000, and a minimum guarantee of $5,000. (R4, tab 1 at 1) 2. The MACC contract incorporated by reference Federal Acquisition Regulation (FAR) 52.249-10, DEFAULT (FIXED PRICE CONSTRUCTION) (APR 1984) (R4, tab 1 at 25). This provision states, in relevant part: If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed FAR 52.249-10(a) 3. The MACC contract established task order (TO) terms as follows: Section 00801(6)(a) provided a base year of 12 months, which the Contracting Officer (CO) could shorten if the maximum contract amount was ordered earlier. Section 801(6)(b) allowed up to four 12-month option periods for a maximum duration of 60 months or until the estimated maximum dollar value was reached, whichever 1 In a footnote, appellant represents that it will submit a claim requesting an extension of time for completion of the project (app. oppân at 2 n.1). However, the record contains no indication of this, nor is there any indication that appellant has filed a separate appeal relating to the contract at issue here. 2 occurred first. The Government could exercise these options by providing written notice during the performance period, with preliminary notice required at least 60 days before contract expiration. (R4, tab 1 at 72-73) Paragraph 2 of Section 00803 of the MACC contract also expressly established an opportunity to compete for task orders, stating in relevant part: â[a]ll awardees will be given a fair opportunity to be considered for each Task Order unless the Contracting Officer applies one of the exceptions noted below.â (R4, tab 1 at 80 (emphasis added)) 4. The MACC contract established a minimum guarantee of $5,000 to each awardee, as follows: The Government makes no representation as to the number of Task Orders or actual amount of work to be ordered, however, during the term of the contract, a minimum of $5,000 is guaranteed to each awardee. Contractors are not guaranteed work in excess of the minimum guarantee specified herein. (Id. at 73) 5. On November 12, 2019, NAVFAC issued Modification No. P0001 to the contract exercising option period one and extending the term of the MACC contract for one year, from November 14, 2019, through November 13, 2020 (R4, tab 2 at 38- 39). 6. On March 16, 2020, NAVFAC awarded to West Point â Granite JV, LLC Task Order No. N62473-20-F-4216, a $14,990,280, firm fixed-price, design-bid-build project for water treatment plant repairs to Basins 343-348 and 352-353 at Naval Air Facility El Centro, El Centro, California. The task order specified a completion date of September 22, 2021. (R4, tab 8 at 54, 56-57). 7. Effective October 6, 2020, NAVFAC and West Point entered into a Change- of-Name Agreement to recognize the contractorâs change of name from West Point - Granite JV, LLC to West Point Utilities, LLC pursuant to the July 27, 2020 amendment to West Point â Granite JV, LLCâs certificate of incorporation (R3, tab 5 at 45-46). Later, on October 27, 2020, NAVFAC issued a modification to the MACC contract, which noted the organizational change and stated that, pursuant to the Change-of-Name Agreement, NAVFAC would issue all subsequent task orders and modifications to West Point Utilities (R4, tab 4 at 43-44 (Modification No. P00003)). 8. In a bilateral modification to the task order, on October 29, 2020, NAVFAC formally changed the contractorâs name to West Point Utilities, LLC, granted a no-cost time extension of 232 days (with a new completion date of May 12, 2022) due to 3 excusable pandemic-related delays impacting financial reporting and bonding, and added a clause prohibiting contracting for certain telecommunications and surveillance equipment. (R4, tab 11 at 716-21 (Modification No. P00002)) 9. On November 12, 2020, NAVFAC issued unilateral Modification No. P00005 to the MACC contract exercising option period two for the period of performance from November 14, 2020, through November 13, 2021 (R4, tab 7 at 52- 53). Cure Notice 10. On March 9, 2021, CO Jessica Garrett issued a Cure Notice citing numerous overdue submittals. The notice warned that failure to address these deficiencies within ten days risked termination for default. At that time, the government estimated West Point was 99 days behind schedule. (R4, tab 15 at 731) 11. On March 19, 2021, West Point responded to the cure notice. West Point acknowledged the project delays, but questioned the need for the cure notice, proposing instead a revised schedule to meet and requesting weekly collaborative meetings to address the underlying causes of delay. West Point blamed the delays on limitations of the Electronic Construction Management System (eCMS) 2 hindering submittal reviews, differing interpretations of contract requirements regarding pre- construction environmental mitigation, and an inefficient submittal review process requiring excessive revisions. (R4, tab 16 at 735-42). 12. The Navy declined to hold weekly meetings involving all NAVFAC stakeholders as requested in West Pointâs March 19, 2021 letter. Although a Navy engineering technician intermittently attended West Pointâs weekly quality control meetings, the Navy did not notify West Point in advance of his attendance. In addition, NAVFAC contracting personnel never held a formal meeting with West Point. (App. oppân, ex. A, Alley decl. ¶¶ 5-6). 2 NAVFAC eCMS is a âweb-based, enterprise project collaboration tool to improve post-award management of schedules, RFIs, designs, and submittals.â It is provided by the Navy at no cost to contractor users associated with a project. See https://www.navfac.navy.mil/Directorates/Planning-Design-and- Construction/About-Us/Planning-Design-and-Construction - Documents/Electronic-Construction-Management-System-eCMS/, last visited August 27, 2025. 4 Show Cause Notice 13. On April 14, 2021, Ms. Garrett issued a show cause notice to West Point. The notice informed West Point that the government was considering terminating the task order for default due to ongoing performance issues, which remain unresolved following the March 9, 2021 cure notice. The show cause notice estimated a current delay of 86 calendar days, reflecting an improvement of 13 days since the March 9, 2021 cure notice. The show cause notice blamed the delay on delinquent and inadequate pre-construction submittals. Although the Navy conceded that it had approved 21 of the 23 required submittals, the Navy blamed West Pointâs quality control for the need to conduct 54 submittal reviews for the submittals, with several critical submittals, including the schedule, repeatedly being disapproved for not conforming to contract requirements. (R4, tab 17 at 743) 14. The show cause notice detailed West Pointâs alleged failure to meet contract requirements related to schedule, quality control, safety, and project management, including an unrealistic schedule, numerous disapproved submittals, unauthorized mobilization of a job site trailer, inadequate safety documentation, and lack of response to prior notices. West Point was given 10 calendar days to respond with any justification for these failures, with non-response considered an admission of fault, and was advised that liquidated damages of $2,919 per calendar day would be assessed. (R4, tab 17 at 744-46) 15. West Point responded on April 23, 2021. West Point disagreed with many of the assertions in the show cause notice and claimed that it omitted key facts. West Point attributed its initial delays to Granite Constructionâs withdrawal from the joint venture and the contracting officerâs insistence that West Point form a new LLC to perform the work. West Point acknowledged that two of the 23 pre-construction submittals remained outstanding, but asserted they were either in the governmentâs possession or subject to other agenciesâ jurisdiction. West Point placed significant blame on NAVFACâs eCMS system for causing delays and inefficiencies in the submittal process, arguing that technical issues and the governmentâs piecemeal review process led to multiple resubmissions. West Point also contended that the COVID-19 pandemic impacted subcontractor availability and material costs and contributed to delays. (R4, tab 18 at 748-51) 16. While acknowledging a current projected completion date two months behind schedule, West Point stated that it could âcontrol its means and methods through acceleration and concurrent work which will enable it to complete the work under this Task Order within the time frame shown in the approved baseline scheduleâ (id. at 751). West Point further stated that it âremains committed to working with the Government towards the successful completion of the work under this Task Order,â and that it was âready, willing and able to complete this projectâ (id.). 5 17. In order to get the project back on schedule, West Point retained additional management personnel and retained an additional subcontractor, Spencer Construction (app. oppân, ex. A, Alley decl. ¶ 9). Termination for Default 18. On May 27, 2021, Ms. Garrett issued to West Point a Notice of Termination for Default â Contracting Officerâs Final Decision. The decision formally terminated the contract for default, citing failures in schedule, quality control, safety, and project management as detailed in the prior show cause notice. (R4, tab 19 at 753) The government rejected West Pointâs explanations for the deficiencies, noting that the government had issued three more non-compliance notices since the show cause notice. The CO stated that, since the show cause notice, West Pointâs failures continued, including âfailing to provide daily reports in a timely manner,â performing work âwithout a Site Safety and Health Officer (SSHO), Quality Control Manager, nor named Activity Hazard Analyses (AHA) competent person onsite,â and repeatedly âfailing to perform Quality Control (QC) requirementsâ (id. at 755). The CO further alleged that West Point demonstrated a âlack of understanding of the workâ by planning to begin demolition of basins prior to dewatering, a critical prerequisite and that demolition activities prior to dewatering could have caused âunstable ground conditionsâ and âcatastrophic loss of facilityâ (id.). The CO argued this oversight, missed due to deficient QC meetings, risked âinjury to construction workersâ and âNAVFAC mission stoppageâ (id.). Finally, the letter outlined West Pointâs appeal rights (id. at 756). 19. On June 16, 2021, the CO issued Modification No. P00003 to the task order terminating it for default based on West Pointâs failure to meet contract requirements (R4, tab 12 at 722-23). 20. On July 21, 2021, a different CO, Tina Collins, sent a notice of intent to not exercise option period three. The notice further stated that the government would not be soliciting additional work from West Point during the remainder of option period two. The notice stated in relevant part: In accordance with the contract clause FAR 52.217-9 entitled Option to Extend the Term of the Contract (MAR 2000), it is the Governmentâs unilateral right whether to exercise the option under the subject contract. The purpose of this letter is to inform you that the Option Period Three for this contract will not be exercised. Also, the Government will not be soliciting any new work to 6 West Point Utilities LLC during the current Option Period Two, which will expire on November 13, 2021. 3 21. On August 20, 2021, West Point timely appealed the termination to the Board, which was docketed as ASBCA No. 63006. 22. On September 24, 2021, West Point filed its complaint, listing two counts as follows: COUNT I (Conversion of Termination for Default to Termination for Convenience) *** 82. As detailed above, West Point Utilities cured any alleged defaults cited by NAVFAC and submitted all required submittals. NAVFAC identified 23 required submittals but also admitted that, at a minimum, 21 of the 23 submittals had been approved by NAVFAC prior to the termination for default. 83. West Point Utilities thus was not in default at the time of termination for the causes identified by NAVFAC. 84. Additionally, West Point Utilities was entitled to extensions of time for excusable delays, as provided by FAR 52.249-10(b), including for delays related to NAVFACâs non-functional eCMS system, COVID-19, and other issues to be proven at trial. 85. As a result of NAVFACâs improper default termination, West Point Utilities has incurred $540,863.91 in damages it had to pay to Harco, its surety, to reimburse Harco for the costs it paid to NAVFAC under the tender agreement. West Point Utilities is entitled to recoup these costs from NAVFAC in addition to West Point Utilities termination for convenience costs 3 This document was not included in the Rule 4 file but was provided by West Point as Exhibit B to its notice of appeal. 7 COUNT II (Breach of Fair Opportunity to Compete) *** 88. NAVFACâs refusal to allow West Point Utilities to participate in future solicitations prior to the expiration of the second option period and rescinding of a solicitation previously sent to West Point Utilities violates IDIQ Contract Section 00803 (Task Order Issuance Procedures), Paragraph 2 (Competition) as well as Section 00802 (Contract Administration Data), Paragraph 4 (Ombudsman). 89. As described by the ASBCA, the âfair opportunity to competeâ clause is an ongoing obligation of the Government, which NAVFAC breached when it expressly refused to allow West Point Utilities to compete on future proposals. See, e.g., Cmty. Consulting Intâl, ASBCA No. 53489, 2002 WL 1788535 (Aug. 2, 2002), relying on Burke Court Reporting Co., DOTBCA No. 3058, 97-2 BCA ¶ 20323. 90. NAVFAC breached the IDIQ Contract by denying West Point Utilities a fair opportunity to Compete and denied West Point Utilities the revenue and profit it could have earned on such projects. 90. NAVFAC breached the IDIQ Contract by denying West Point Utilities a fair opportunity to Compete and denied West Point Utilities the revenue and profit it could have earned on such projects. 91. Accordingly, NAVFAC is liable to West Point Utilities for the anticipated profits and unallocated home office overhead it could have obtained had NAVFAC afforded West Point Utilities the mandatory opportunity to bid on and perform task orders under the IDIQ Contract. DECISION The Navyâs Motion to Dismiss for Lack of Jurisdiction/Motion to Strike The Navy moves to strike West Pointâs assertions, contained in Count I, ¶¶ 82- 84 of the Complaint relating to its excusable delay defense and entitlement to time extensions, for lack of jurisdiction due to the failure to file a valid claim with the 8 contracting officer (govât mot. at 12). Additionally, the Navy moves to strike ¶ 85 of Count I, relating to $540,863.91 in damages West Point allegedly had to pay Harco, its surety, for lack of jurisdiction for the same reason as the previously mentioned paragraphs (govât mot. at 15). Regarding Count II, the Navy argues that West Point failed to submit a proper claim to the contracting officer relating to unspecified lost revenue, anticipated profits, and unallocated home office overhead costs related to the Navyâs alleged breach of the âfair opportunity to compete clauseâ as asserted in ¶¶ 88- 91 of the Complaint. As such, the Navy avers that the Board lacks jurisdiction over the allegations, and they should be stricken from the Complaint. (Govât mot. at 15-16) West Point counters that the Board has jurisdiction over all of the issues the Navy seeks to strike. Specifically, it alleges that the government is required to consider the factors listed in FAR 49.402-3(f) in its decision to terminate a contract for default, including all excuses relating to non-performance. (App. reply at 6) Thus, West Point contends that the Board should allow it the opportunity to present evidence âof both excusable delays, and the [COâs] failure to consider them, in connection with the Governmentâs case-in-chiefâ (id. at 9-10). Additionally, West Point avers that the Board has jurisdiction to consider its âfair opportunity to competeâ claim because it arises out of the government claims (e.g. the termination for default and the refusal to allow West Point to compete for further work under the contract) and a final decision was issued (id. at 14). The Navy responded that the notice of intent not to exercise the option was not a government claim and the contract did not guarantee West Point more than the minimum guarantee (govât reply at 9-12). I. Governmentâs Motion to Dismiss or Strike Counts I and II of Appellantâs Complaint A. Standard of Review West Point bears the burden of establishing the Boardâs jurisdiction under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, by a preponderance of the evidence. Parsons Global Servs., Inc., ASBCA No. 56731, 11-1 BCA ¶ 34,632 at 170,653 (citing Reynolds v. Army & Air Force Exch. Servs., 846 F.2d 746, 748 (Fed. Cir. 1988)). West Point must demonstrate that it is more likely than not that the Board possesses jurisdiction to entertain this appeal. B. Whether the Board Possesses Jurisdiction to Entertain Appellantâs Affirmative Defense of Excusable Delay The government contends that the Board lacks jurisdiction to entertain West Pointâs claims of excusable delay as a defense against the termination for default without first presenting the delay claims to the CO. Therefore, the government 9 requests the Board dismiss the excusable delay allegations set forth in Count I, ¶¶ 82- 84 of West Pointâs complaint. (Govât mot. at 12-14) West Pointâs response challenges the merits of the governmentâs decision to terminate the contract for default, contending that the government failed to adequately consider the mandatory factors set forth in FAR 49.402-3(f). West Point argues that these factors include excusable delay and West Pointâs progress in curing deficiencies. West Point further contends that the CO was aware of problems with the governmentâs electronic submittal program and the widespread impacts of COVID-19 and that the government terminated the contract prematurely despite West Point having a significant portion of the performance period remaining. (App. oppân at 4-13, 20 (response to govât SUMF ¶ 24), 28-33 (app. statement of additional material facts ¶¶ 9.b, 20.b); ex. A ¶¶ 7.b, 19.b) Specifically, West Point argues that the FAR expressly requires the government to consider all excuses to non-performance, regardless of whether the contractor is entitled to a time extension for excusable delay (app. oppân at 6). FAR 49.402-3(f) enumerates seven factors that the CO âshall consider,â including âthe excuses for the failureâ to perform and âany other pertinent facts and circumstancesâ (id. at 4-5). Appellant cites to several cases holding that the COâs failure to consider these factors supports converting the default termination into one for convenience (id.at 5-6). The CDA mandates that contractors submit all contract claims against the government to the CO for a decision. 41 U.S.C. § 7103(a)(1). Consequently, the essential element of the Boardâs jurisdiction over a contractorâs claim is the contractorâs submission of a proper claim to the CO for a decision. JAAAT Tech. Servs., Inc., ASBCA No. 61792 et al., 21-1 BCA ¶ 37,878 at 183,953; Air Servs., Inc., ASBCA No. 59843, 15-1 BCA ¶ 36,146 at 176,424. A contractor is required to submit a certification to the CO for any claim exceeding $100,000. WIT Assocs., Inc., ASBCA No. 61547, 19-1 BCA ¶ 37,226 at 181,210. The Board cannot entertain an appeal that exceeds $100,000 if the claim is not certified. Al Rafideen Co., ASBCA No. 59156, 15-1 BCA ¶ 35,983 at 175,808; Bell Helicopter Textron Inc. & The Boeing Co., ASBCA No. 59561, 15-1 BCA ¶ 36,111 at 176,291. Here, West Point admits in its opposition to the Navyâs motion that it has not presented a certified claim to the CO asserting the excusable delay defense alleged in its complaint (app. oppân at 21 (responding to govât proposed statement of undisputed facts (govât SUMF) ¶ 24)) (stating that âWest Point does not dispute that it has not submitted claims as identified in subparagraphs (b) and (c) of this Paragraph.â). West Pointâs failure to properly assert a CDA claim for excusable delay bars it from raising excusable delay as an affirmative defense. Under binding Federal Circuit precedent, a contractor seeking to alter the terms of a contract â such as by obtaining a time extension â must first submit that request as a certified claim to the CO, even 10 when asserting it as an affirmative defense to a government action. In Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323 (Fed. Cir. 2010), the Federal Circuit held that âa contractor seeking an adjustment of contract terms must meet the jurisdictional requirements and procedural prerequisites of the CDA, whether asserting the claim against the government as an affirmative claim or as a defense to a government action.â Id. at 1331 (emphasis added). The Federal Circuit subsequently applied this rule in the context of a default termination in Securiforce Intâl. Am., LLC v. United States, 879 F.3d 1354 (Fed. Cir. 2018), overruled, in part, on other grounds, ECC Intâl Constructors, LLC v. Secây of Army, 79 F4th 1364 (Fed. Cir. 2023). While holding that a defense of prior material breach need not be submitted to the CO, the court reiterated that any affirmative defense seeking a change in contract terms (like a time extension) must be presented to the CO first. Securiforce, 879 F.3d at 1363. The Board has applied the rule set forth in Maropakis and Securiforce to bar consideration of excusable delays as affirmative defenses to a termination for default. In ECC CENTCOM Constructors, 18-1 BCA ¶ 37,133 at 180,711-713, the Board held that a contractorâs failure to submit claims for alleged excusable delays barred consideration of those delays as affirmative defenses to a termination for default. Likewise, in Cobeal Consulting Grp., ASBCA No. 63815, 25-1 BCA ¶ 38,742 at 188,340, recon. denied, Slip. Op. July 30, 2025, the Board dismissed appellantâs claims for damages for increased costs, improper liquidated damages, and several time extensions in connection with its challenge of a termination for default, on the grounds that they were not presented to the CO for a decision. See also DCX-CHOL Enters., Inc., ASBCA Nos. 61636, 61637, 19-1 BCA ¶ 37,394 at 181,800, recon. granted in part, 20-1 BCA ¶ 37,483 at 182,068 (striking affirmative delay and constructive change defenses for failure to present as claims before the CO); Windamir Dev., Inc., ASBCA No. 63461, 24-1 BCA ¶ 38,484 at 187,044 (striking affirmative defense of delay for lack of jurisdiction). West Point does not attempt to distinguish or contradict the legal authorities relied on by the government. Instead, West Point raises a host of arguments going to the merits of the governmentâs decision to terminate the contract for default (app. oppân at 4-12). While an agencyâs adherence to the factors in FAR 49.402-3(f) informs our assessment of whether a default termination constitutes an abuse of discretion, consideration of these factors is not required for a valid termination. ECC CENTCOM Constructors, 18-1 BCA ¶ 37,133 at 180,715 (citing DCX, Inc. v. Perry, 79 F.3d 132, 135 (Fed. Cir. 1996)). The regulations do not establish rights for the defaulted contractor, and a COâs failure to consider any particular factor does not necessitate converting a default termination to one for convenience. GSC Constr., Inc., ASBCA Nos. 59402, 59601, 21-1 BCA ¶ 37,751 at 183,227. We acknowledge appellantâs arguments concerning the FAR requirements for termination, but these contentions go the merits of the governmentâs claim and are premature at this stage of proceedings. 11 Because West Point failed to submit a certified claim to the CO regarding excusable delays, as required by the CDA, the Board lacks jurisdiction to consider those delays as an affirmative defense against the governmentâs termination for default. Based on the fact that only ¶ 84 of the Complaint alleges that West Point was entitled to extensions of time for excusable delays, we grant the governmentâs motion to dismiss for lack of jurisdiction and to strike the allegation set forth in ¶ 84 of West Pointâs Complaint. C. Whether the Board Possesses Jurisdiction to Entertain Appellantâs Request to Recoup Money Paid to its Surety The government next contends that the Board lacks jurisdiction to entertain West Pointâs claim to recoup $540,863.91 paid to its surety, as set forth in ¶ 85 of its Complaint, because West Point never submitted a certified claim for this amount to the CO for a final decision (govât mot. at 14-15). In response, West Point admits that it has not submitted a claim to the CO for the $540,863.91 that West Point paid to its surety (govât mot. at 8; app. oppân at 21 (responding to govât SUMF ¶ 24(b)). However, West Point asserts that it is not seeking those costs at this time, but rather intends to include them in a cost proposal to be implemented if the default termination is converted to a termination for convenience (app. oppân at 13). West Point further argues that the costs paid to its surety are evidence that the CO failed to properly consider factors set forth in FAR 49.402-3(f) before terminating the contract â specifically the urgency of the need and the time required to obtain services from other sources compared to the original contractor. According to West Point, these costs demonstrate the COâs abuse of discretion in the termination decision. Id. Our analysis focuses on the allegations set forth in West Pointâs complaint. Paragraph 85 of the complaint states: As a result of NAVFACâs improper default termination, West Point Utilities has incurred $540,863.91 in damages it had to pay to Harco, its surety, to reimburse Harco for the costs it paid to NAVFAC under the tender agreement. West Point Utilities is entitled to recoup these costs from NAVFAC in addition to West Point Utilities termination for convenience costs. West Point states in its opposition that it is not seeking these costs in this appeal and that this statement merely indicates that West Point intends to seek these costs in its termination for convenience settlement proposal (app. oppân at 13). The government 12 contends, however, that Paragraph 85 is a claim for money damages that cannot be sustained without first being presented to a CO. By asking for the amount of $540,863.91 âin addition toâ the termination costs, paragraph 85 is a straightforward request for money damages. Because West Point admits that it has not filed a certified claim with the CO for this amount, we lack jurisdiction to entertain this allegation. Accordingly, we strike paragraph 85 of the complaint, as well the language in the final paragraph of the complaint asking the Board âto include the costs West Point Utilities reimbursed to Harco under the tender agreementâŠâ (Compl. at 16). We note that our decision to strike the allegations of paragraph 85 from the Complaint does not prevent West Point from relying upon these factual allegations to support its defense of the default termination, or from requesting these costs in its termination for convenience settlement proposal. Moreover, our decision does not prevent West Point from filing a claim for these costs with the CO. II. Whether the Board Possesses Jurisdiction to Entertain Count II of Appellantâs Complaint A. The Partiesâ Arguments The government next moves to dismiss Count II of West Pointâs complaint, which addresses West Pointâs allegations that the Navy breached West Pointâs IDIQ contract by refusing to allow West Point to participate in future solicitations (compl. ¶¶ 87-91). According to the government, the Board lacks jurisdiction over Count II because West Point failed to submit a claim to the CO requesting a final decision on its entitlement to unspecified amounts for lost revenue, anticipated profits, and unallocated home office overhead resulting from that alleged breach. (Govât mot. at 15-16) West Point argues that the Navyâs July 21, 2021 notice, refusing to solicit new work from West Point during option period two, constructively terminated their IDIQ contract and constitutes a government claim. West Point contends that this permits a direct appeal to the Board without a CO claim. (App. oppân at 14-18, 21) West Point distinguishes between the Navyâs obligation to award work and its obligation to allow competition for work (app. oppân at 15). Citing Community Consulting Intâl, ASBCA No. 53489, 02-2 BCA ¶ 31,940, appellant contends that the Navyâs refusal to allow appellant to compete is a triable issue regarding breach of the MACC IDIQ contract and that the award of a guaranteed minimum did not relieve the government of other contractual obligations (app. oppân at 15-16). 13 In its reply, the government contends its July 2021 notice informing West Point it would not solicit further work is not a âclaimâ under the CDA. The government bases its argument on the CDA and FAR definition of a claim, which requires a written demand or assertion as a matter of right for a specific sum of money, an adjustment or interpretation of contract terms, or other relief stemming from the contract (govât reply at 9 (citing FAR 52.233-1). The government points to Board precedent where we have stated or found government claims include demands for refunds, corrective work orders, requests to review records, claims for excess re- procurement costs, and unilateral contract modifications reducing price (id. at 9-10). The government argues that the July 2021 notice is not a claim, because it did not demand a specific action like payment or contract modification, nor was it a final decision by a contracting officer. Consequently, the Navy contends that West Point should have submitted a claim to the CO before appealing to the Board. (Id. at 10) B. Refusal to Solicit Further Work is Not a Constructive Termination if the IDIQ Minimum Has Been Met Refusal to solicit further work under an IDIQ contract does not constitute a termination, constructive or otherwise, as long as the government has fulfilled its minimum purchase obligation. It is established that once the government meets the contract minimum set in an IDIQ contract, it has no further legal obligations under the contract. Varilease Tech. Group, Inc. v. United States, 289 F.3d 795, 800-01 (Fed. Cir. 2002); Travel Ctr. v. Barram, 236 F.3d 1316, 1319 (Fed. Cir. 2001). Moreover, as the Federal Circuit held in Varilease, minimum quantities are not required to be associated with each option period. Varilease, 289 F.3d at 800; see also RJO Enterprises, Inc., ASBCA No. 50981, 03-1 BCA ¶ 32,137 at 158,907-08 (holding that minimum quantities in an IDIQ contract are not required to be associated with each option period). Here, the government ordered more than the minimum quantity of $5,000 from West Point and has fulfilled its legal obligations under the MACC IDIQ contract (SOF ¶ 6). Therefore, its stated refusal to solicit additional work during the remainder of option period two does not constitute a constructive termination. Community Consulting offers West Point no assistance. In that appeal, appellant submitted a claim to the CO alleging a breach of the fair opportunity to compete. Community Consulting, 02-2 BCA ¶ 31,940 at 157,786. At issue was whether the Board possessed jurisdiction to entertain the claim on the grounds that it was essentially a bid protest, rather than a claim of contractual breach. The Board concluded that the claim was an alleged contractual breach, not a bid protest, and that it possessed jurisdiction to entertain the claim of breach. Id. at 157,786-87. Crucially, the Board was not presented with the question of whether the alleged breach of the opportunity to compete was a constructive termination, because the appellant had submitted a predicate claim to the CO. 14 Here, unlike in Community Consulting, West Point has not submitted a claim to the CO alleging a breach of the MACC contract. Therefore, West Point cannot rely upon Community Consulting to support its contention that an alleged breach of the fair opportunity to complete is a constructive termination or, more generally, a government claim. Moreover, we have found no Federal Circuit or Board precedent holding that a notice refusing to solicit further work under an IDIQ contract constitutes a constructive termination of that contract. Paragraph 2 of Section 00803 of the MACC contract expressly established an opportunity to compete for task orders, stating in relevant part: â[a]ll awardees will be given a fair opportunity to be considered for each Task Order unless the Contracting Officer applies one of the exceptions noted below.â (SOF ¶ 3 (emphasis added) None of the contractâs limited exceptions (extreme urgency, sole source justification) apply here. While West Point argues the July 21 notice breached this fair opportunity provision, this potential breach does not constitute a separate government claim. Therefore, lacking a certified claim presented to the CO pursuant to 41 U.S.C. § 7103(a)(1), we lack jurisdiction. West Point must first submit a claim to the CO to pursue this breach allegation before the Board. Accordingly, we grant the Navyâs motion to strike Count II. C. Whether the Navy is Entitled to Summary Judgment on Count II As an alternative argument, the Navy argues that the Board should grant summary judgment on Count II because West Point cannot state a valid claim for relief under the âFair Opportunity to Complete Clause.â While acknowledging that the government met its contractual minimum award obligations, West Point contends this does not relieve the government of its duty to provide fair opportunity to compete for additional work (app. oppân at 15-16). Citing Community Consulting and Burke Court Reporting Co., DOT BCA No. 3058, 97-2 BCA ¶ 29,323, West Point argues that meeting minimum quantities under indefinite quantity contracts does not eliminate other contractual obligations, including the implied duty of good faith and express contractual requirements for fair consideration. Id. at 17. West Point further contends that the July 21, 2021 letter also serves as the governmentâs final decision, as it was adverse to the contractor and appealable regardless of lacking standard appeal language, providing the Board with proper jurisdiction over the claim. Id. at 18. Because we hold that Count II should be dismissed for lack of jurisdiction, we need not address the Navyâs alternative argument for summary judgment. We note, however, that nothing precludes West Point from filing a claim with the CO raising the same allegations of breach of the fair opportunity to compete. 15 III. Governmentâs Motion for Summary Judgment on Termination for Default The Navy moves for summary judgment upholding the termination for default on two alternative grounds. First, the Navy contends that it has satisfied the standard in FAR 52.249-10(a) by demonstrating that the CO was âjustifiably insecure about the contractâs timely completionâ (govât mot. at 18 (citing FFR-Bauelemente + Bausanierung GmbH, ASBCA No. 52152 et al., 07-2 BCA ¶ 33,627)). Specifically, the Navy contends that the CO reasonably believed West Point could not complete the project on time due to acknowledged delays, a lack of a viable recovery plan, and concerns about West Pointâs experience and approach to crucial tasks like dewatering (id. at 19-20). Alternatively, the Navy contends that West Point failed to provide adequate assurances of timely completion in response to cure notices, offering only vague and unsubstantiated claims, and that West Pointâs failure amounted to an anticipatory repudiation of the contract. Id. at 20-21. The Navy concludes that the contractâs default clause, coupled with West Pointâs performance failures and lack of credible assurances, warrants upholding the termination. Id. at 21. A. Legal Standard We grant summary judgment only when no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). The Navy, as the moving party, bears the burden of establishing the absence of any genuine factual dispute. Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed. Cir. 1987). We must resolve all factual disputes and draw all reasonable inferences in favor of West Point. Sauer Constr. LLC, ASBCA No. 63738, 25-1 BCA ¶ 38,744 at 188,344 (citing Mingus, 812 F.2d at 1390-91). Under FAR 52.249-10(a), the government may terminate a contract for default when the contracting officer reasonably believes the contractor cannot complete performance on time. The test is whether the CO held an objectively reasonable belief that there was no reasonable likelihood of timely completion. Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 765 (Fed. Cir. 1987); DODS, Inc., ASBCA Nos. 57746, 58252, 14-1 BCA ¶ 35,677 at 174,624 (citing Lisbon). The government cannot terminate âmerelyâ for being behind scheduleâit must demonstrate no reasonable prospect of timely completion. Lisbon, 828 F.2d at 765. B. Summary Judgment is Not Appropriate Because genuine disputes of material fact exist concerning the contractorâs progress, recovery efforts, and the COâs consideration of FAR 49.402-3(f) factors, 16 summary judgment is inappropriate at this stage of the appeal. West Point has submitted evidence that, construed in the light most favorable to West Point, suggests that its performance was actually improving over time, with delays decreasing from 99 days to 86 days to just 60 days by termination. (App. oppân, ex. A¶ 8) With nearly a year remaining on the contract, this trajectory raises factual questions about the reasonableness of the COâs pessimistic assessment. West Point also asserts that it resolved 21 of the 23 problematic submittals and took concrete remedial actions including hiring additional management personnel and retaining Spencer Construction as an additional subcontractor. (SOF ¶¶ 15, 17; app. oppân at 19-20 (response to govât SUMF ¶ 14, 32)). Whether these actions provided reasonable assurances of timely completion is a disputed factual question, a key consideration under Lisbon. The parties dispute whether West Point failed to provide adequate recovery planning. West Point claims the Navy refused to meet to discuss a prepared recovery schedule, while the Navy contends no viable schedule was submitted. The partiesâ dispute over recovery planning goes to whether the CO reasonably concluded there was no reasonable prospect of timely completion. In addition, West Point has raised facts suggesting that the Navy failed to consider the factors set forth in FAR 49.402-3(f). In particular, West Point alleges that the CO did not consider excusable delays as required in FAR 49.402-3(j), failed to consult with the Small Business Administration as mandated for small business contractors, and failed to evaluate the other factors in FAR 49.402-3(f) before termination. (App. oppân at 31-32) Although the failure to consider a specific factor does not automatically invalidate a termination for default and does not confer rights on the contractor, the factors may aid the Board in evaluating the reasonableness of the COâs decision. DCX, Inc., 79 F.3d at 135. Under Lisbon, the critical question is whether the COâs determination that timely completion was impossible was objectively reasonable. West Pointâs improving performance metrics, documented remedial actions, and substantial remaining contract time create genuine factual disputes about this reasonableness determination. These disputes must be resolved at trial, not on summary judgment. C. The Government Has Not Established Anticipatory Repudiation To prove anticipatory repudiation, the government must show the contractor communicated a positive, definite, and unconditional intent not to perform through either: (1) a definite and unequivocal statement refusing to perform; or (2) actions constituting actual abandonment. Highland Al Hujaz Co., Ltd., ASBCA No. 58243, 16-1 BCA ¶ 36,336 at 177,165 (citations omitted). 17 Either an express refusal to perform or a statement of inability to perform may constitute anticipatory repudiation. See Danzig v. AEC Corp., 224 F.3d 1333, 1339-40 (Fed. Cir. 2000) (holding that the failure to provide assurances of performance is a breach justifying termination for default). For example, stating inability to perform unless the government modifies the contract constitutes anticipatory repudiation. LKJ Crabbe Inc., ASBCA No. 60331, 18-1 BCA ¶ 37,193 at 181,065; Symvionics, Inc., ASBCA Nos. 60335, 60612, 17-1 BCA ¶ 36,790 at 179,322 (citing Cascade Pacific Intâl v. United States, 773 F.2d 287, 293 (Fed. Cir. 1985)). The Navyâs anticipatory repudiation argument fails because West Point consistently expressed an intent to perform and complete on time. West Point responded to the March 9, 2021 cure notice within 10 days, proposing a revised schedule for collaborative meetings to address the underlying causes of the delay (SOF ¶ 11). West Point responded to the April 14, 2021 show cause notice within nine days, stating that it believed there were ways to âcontrol its means and methods through acceleration and concurrent work which will enable it to complete the work under this Task Order within the time frame shown in the approved baseline schedule.â (SOF ¶ 16) West Point further stated that it âremains ready, willing and able to complete this projectâ (id.). These statements demonstrate intent to complete the project on time and fall short of the required âdefiniteâ and âunequivocalâ intent not to perform. The Navy makes too much of West Pointâs admission in its response to the show cause notice that the current project tracked two months behind the baseline schedule (govât reply at 16). This statement falls well short of the statements made in Danzig, where the contractor admitted in its response to the governmentâs cure notice that its financial difficulties ââmade it impossible . . . to predict an ultimate completion date at this time.ââ 224 F. 3d at 1335, 1338. The contractor in Danzig further admitted that, unless its surety released funds in the projectâs bank account, ââit is doubtful that [we] will ever be able to complete the project.ââ Id. Moreover, the contractor in Danzig reduced its work force to just two employees and failed completely to respond to the governmentâs subsequent show cause notice within the 10-day deadline. Id. at 1339. West Point, in contrast, timely responded to both the cure notice and the show cause notice (SOF ¶¶ 11, 16). It also stated that it was willing and able to complete the project and had developed a plan to do so within the original deadline (SOF ¶16). Finally, West Point took concrete steps to address the delay by retaining additional management personnel and retaining an additional subcontractor (SOF ¶ 17; app. oppân at 19-20 (response to govât SUMF ¶ 14)). The facts, viewed most favorably to West Point, preclude summary judgment for the Navy. 18 CONCLUSION Because West Point failed to submit claims to the CO as required by the Contract Disputes Act, ¶¶ 84, 85, and Count II (¶¶ 88-91) are dismissed without prejudice due to lack of jurisdiction. However, the Board denies the governmentâs motion for summary judgment on the termination for default, finding genuine issues of material fact regarding the reasonableness of the termination and anticipatory repudiation that preclude summary judgment. Dated: September 4, 2025 KENNETH D. WOODROW Administrative Judge Armed Services Board of Contract Appeals I concur I concur OWEN C. WILSON MICHAEL N. OâCONNELL Administrative Judge Administrative Judge Acting Chairman Vice Chairman Armed Services Board Armed Services Board of Contract Appeals of Contract Appeals 19 I certify that the foregoing is a true copy of the Opinion and Decision of the Armed Services Board of Contract Appeals in ASBCA No. 63006, Appeal of West Point Utilities, LLC, rendered in conformance with the Boardâs Charter. Dated: September 4, 2025 PAULLA K. GATES-LEWIS Recorder, Armed Services Board of Contract Appeals 20
Case Information
- Court
- A.S.B.C.A.
- Decision Date
- September 4, 2025
- Status
- Precedential